A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed. Which project artifact should the risk manager analyze to mitigate the ris…
Nội dung câu hỏi
A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed. Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Contingency reserves
- B. Schedule and resource assumptions
- C. Work breakdown structure (WBS) — đáp án hiện tại
- D. Risk impact matrix