Câu 65: PMI Risk Management Professional

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk. What should the team perform in this scenario?

Nội dung câu hỏi

The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk. What should the team perform in this scenario?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Quantitative risk analysis — đáp án hiện tại
  2. B. Risk urgency assessment
  3. C. Monitor and control risks
  4. D. Risk response planning