A project manager was informed that the testing of the latest component in the project’s software update release was not successful. As a result, the delivery timelines for the software release will be delayed. The project manager did not previously capture this as a risk to the project. What should the project manage…

Nội dung câu hỏi

A project manager was informed that the testing of the latest component in the project’s software update release was not successful. As a result, the delivery timelines for the software release will be delayed. The project manager did not previously capture this as a risk to the project. What should the project manager do next to avoid similar risks?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Add contingencies to other tasks to mitigate similar risks.
  2. B. Review the risk response plan looking for lessons learned.
  3. C. Reassess risks with a new assumptions and constraints analysis. — đáp án hiện tại
  4. D. Log the event in the issue log and update the project management plan.