Câu 66: PMI Risk Management Professional
A project manager was informed that the testing of the latest component in the project’s software update release was not successful. As a result, the delivery timelines for the software release will be delayed. The project manager did not previously capture this as a risk to the project. What should the project manage…
Nội dung câu hỏi
A project manager was informed that the testing of the latest component in the project’s software update release was not successful. As a result, the delivery timelines for the software release will be delayed. The project manager did not previously capture this as a risk to the project. What should the project manager do next to avoid similar risks?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Add contingencies to other tasks to mitigate similar risks.
- B. Review the risk response plan looking for lessons learned.
- C. Reassess risks with a new assumptions and constraints analysis. — đáp án hiện tại
- D. Log the event in the issue log and update the project management plan.
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.