Câu 67: PMI Risk Management Professional
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50,000. Risk B has a probability of 0.7 and an impact of US$60,000. After implementing the planned risk response for risk B, the probability of risk B has been…
Nội dung câu hỏi
An IT project is 40% complete. During the initial analysis, risks A and B were identified for the project. Risk A has a probability of 0.6 and an impact of US$50,000. Risk B has a probability of 0.7 and an impact of US$60,000. After implementing the planned risk response for risk B, the probability of risk B has been reduced to 0.3. What is the current project risk exposure?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. US$30,000
- B. US$72,000
- C. US$48,000 — đáp án hiện tại
- D. US$18,000