Câu 89: PMI Risk Management Professional
A project's risk manager successfully implements the risk management plan and the risk register. Furthermore, the risk analysis and the risk response planning are finalized. All results have been documented, and the project management plan and other project documents have been updated accordingly. What should the risk…
Nội dung câu hỏi
A project's risk manager successfully implements the risk management plan and the risk register. Furthermore, the risk analysis and the risk response planning are finalized. All results have been documented, and the project management plan and other project documents have been updated accordingly. What should the risk manager do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Perform a lessons learned document update with the defined risks.
- B. Perform regular reserve analysis to ensure that the assigned risk reserve budgets are sufficient.
- C. Perform risk date quality assessments.
- D. Perform continuous risk re-evaluation throughout the project life cycle to ensure risk management effectiveness. — đáp án hiện tại