During the execution of a multi-million dollar project, the project manager learns of the theft of important installation materials at one of the most time-critical sites. The project manager contacts the risk manager to discuss further steps, based on the risk register and the defined risk strategy for the risk of th…

Nội dung câu hỏi

During the execution of a multi-million dollar project, the project manager learns of the theft of important installation materials at one of the most time-critical sites. The project manager contacts the risk manager to discuss further steps, based on the risk register and the defined risk strategy for the risk of theft. However, the risk manager clarifies that the risk of theft was not identified in the risk management process. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Deal with the issue and instruct the risk manager to include the risk of theft in the issue log.
  2. B. Update the project schedule and inform the stakeholders about the project schedule delay.
  3. C. Instruct the risk manager to transfer the risk of theft to an insurance company and capture the experience in the lessons learned. — đáp án hiện tại
  4. D. Make the risk manager responsible for the damage caused by the missing risk strategy for theft and update the project schedule.