Câu 159: PMI Risk Management Professional
The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin. The project manager would like the risk manager to take full advantage of opportunities. Which response should the risk manager take?
Nội dung câu hỏi
The project director and project manager have met with the board and determined that the project has depleted the entire contingency reserve and has started eroding the profit margin. The project manager would like the risk manager to take full advantage of opportunities. Which response should the risk manager take?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Accept
- B. Mitigate
- C. Transfer
- D. Exploit — đáp án hiện tại