During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk. What should the risk manager do to handle this situation?
Nội dung câu hỏi
During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk. What should the risk manager do to handle this situation?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Ask the project sponsor for more budget to deal with this risk.
- B. Revisit this risk in the risk register and redefine the mitigation strategy. — đáp án hiện tại
- C. Mark this new risk as an extremely high priority and inform all stakeholders.
- D. Activate the contingency plan to handle this risk during execution.