Câu 162: PMI Risk Management Professional

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives. What should the risk manager do to facilitate the sponsor’s ask?

Nội dung câu hỏi

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives. What should the risk manager do to facilitate the sponsor’s ask?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Quantitative risk analysis
  2. B. Sensitivity analysis — đáp án hiện tại
  3. C. Qualitative risk analysis
  4. D. Monte Carlo analysis