Câu 38: PMI Risk Management Professional
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?
Nội dung câu hỏi
The senior risk manager hears that critical deliverables are delayed, because a key subject matter expert (SME) does not have enough time to allocate to the tasks. Which area should be reviewed, as an opportunity for the risk manager to coach the project manager responsible for the project?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Scope reduction to reduce SME reliance
- B. Risk management plan and planned risks responses
- C. Risk identification process and participation — đáp án hiện tại
- D. Detailed review of the project schedule before approval
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.