Câu 37: PMI Risk Management Professional

Very low = 1, Low = 2, Moderate = 3, High = 4, Very High = 5A project manager must complete a report for a stakeholder who is concerned about the possibility of a funding shortfall. What is the most effective way to explain the risk to this stakeholder?

Nội dung câu hỏi

Very low = 1, Low = 2, Moderate = 3, High = 4, Very High = 5A project manager must complete a report for a stakeholder who is concerned about the possibility of a funding shortfall. What is the most effective way to explain the risk to this stakeholder?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The funding shortage is the lowest ranked/scored risk.
  2. B. The funding shortage is a significant risk.
  3. C. The funding shortage will have a very high impact on the project and is the highest priority.
  4. D. The funding shortage has a very low probability of occurring and is not a concern for the project. — đáp án hiện tại