A well-established project begins to experience cost overruns and falls behind schedule. The project risk register identifies many risks and risk response plans in place, yet many risks are transitioning into issues. As the risks occur and become issues, many of the response plans are in progress, but not complete. Th…
Nội dung câu hỏi
A well-established project begins to experience cost overruns and falls behind schedule. The project risk register identifies many risks and risk response plans in place, yet many risks are transitioning into issues. As the risks occur and become issues, many of the response plans are in progress, but not complete. The data from this graph represents the status of the project risks. Based on this information, what improvement to the risk management process is required?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Increase the project risk identification and analysis.
- B. Improve the risk analysis to better define root causes. — đáp án hiện tại
- C. Transition to an issue management program and close the remaining open risks.
- D. Review remaining risk response plans and invest in schedule quality improvements.