Câu 28: PMI Risk Management Professional
A risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex, but has rigorous implementation timelines, and very little cost reserve available to address potential problems. The project manager indicates that completing the project on time is critical, but sho…
Nội dung câu hỏi
A risk manager is assigned to a short-term telecommunications upgrade project. This project is not technically complex, but has rigorous implementation timelines, and very little cost reserve available to address potential problems. The project manager indicates that completing the project on time is critical, but should not be done at the expense of performance. Which aspect of risk impact is most important when designing the risk impact scale?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Technical performance — đáp án hiện tại
- B. Cost
- C. Technical requirements
- D. Schedule
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.