Câu 29: PMI Risk Management Professional

During a major project review, the project manager discovers that large groups of internal management issues are obstructing progress. In reviewing the risk management plan, the project risk categories largely contain technical and customer relationship type risks. The project manager wants the risk management plan re…

Nội dung câu hỏi

During a major project review, the project manager discovers that large groups of internal management issues are obstructing progress. In reviewing the risk management plan, the project risk categories largely contain technical and customer relationship type risks. The project manager wants the risk management plan revised to account for these risk areas, particularly because the project has several more months before completion. Who should the project manager collaborate with to revise the risk management plan at this stage of the project?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Risk manager, technical manager, and customers — đáp án hiện tại
  2. B. Project sponsor, product owner, and risk owners
  3. C. Risk manager, product owner, and risk owners
  4. D. Risk manager, risk owners, and project sponsor