Câu 88: PMI-SP: PMI Scheduling Professional Practice Test
You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for moving materials. You also have to ensure that delivery trucks do not have to wait in a queue and that workers on the upper floors are abl…
Nội dung câu hỏi
You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for moving materials. You also have to ensure that delivery trucks do not have to wait in a queue and that workers on the upper floors are able to get their deliveries on time. Which type of scheduling would be required in such a scenario?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Critical path scheduling
- B. Time-oriented scheduling
- C. Resource-oriented scheduling — đáp án hiện tại
- D. Network scheduling
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.