CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 87: PMI-SP: PMI Scheduling Professional Practice Test

Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim is adding a few hours to the duration estimate in case something goes wrong during the completion of the work activity. Sarah, the project sponsor, does not…

Nội dung câu hỏi

Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim is adding a few hours to the duration estimate in case something goes wrong during the completion of the work activity. Sarah, the project sponsor, does not approve of this and warns Jim of Parkinson's Law. What is Parkinson's Law?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. People will behave based on what their behavior brings them.
  2. B. As employees do repetitive tasks, duration should decrease.
  3. C. Work expands to fill the amount of time allotted to it. — đáp án hiện tại
  4. D. An exponential increase labor does not correlate to an exponential decrease in duration.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề