CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 86: PMI-SP: PMI Scheduling Professional Practice Test

Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

Nội dung câu hỏi

Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. -$75,500
  2. B. -$390,000
  3. C. -$487,500
  4. D. -$65,000 — đáp án hiện tại

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề