You are the project manager of the NHG. The following figure represents your project network diagram. Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affectActivity I. The duration of Activity I, which is on the critical pat…

Nội dung câu hỏi

You are the project manager of the NHG. The following figure represents your project network diagram. Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affectActivity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

Minh họa câu hỏi

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The critical path will now take 26 days.
  2. B. The critical path will now take 17 days.
  3. C. The critical path will now take 23 days. — đáp án hiện tại