CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 56: PMI-SP: PMI Scheduling Professional Practice Test

Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Manag…

Nội dung câu hỏi

Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Project calendar — đáp án hiện tại
  2. B. Activity attributes
  3. C. Resource calendar
  4. D. Schedule management plan

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề