Câu 214: Project Management Professional (PMBOK 6 and 7)

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor management team will not derive any benefits from the project. However, the project requires support from the vendor management head. What should the project manager do next?

Nội dung câu hỏi

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor management team will not derive any benefits from the project. However, the project requires support from the vendor management head. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.
  2. B. Review the terms of reference of the steering committee to include the vendor management head.
  3. C. Work with the sponsor on a communications management plan to obtain support from the vendor management head. — đáp án hiện tại
  4. D. Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.