Câu 213: Project Management Professional (PMBOK 6 and 7)

A large multi-year project requires highly skilled staff for successful deployment. The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun. However, there is a risk of staff turnover during the cours…

Nội dung câu hỏi

A large multi-year project requires highly skilled staff for successful deployment. The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun. However, there is a risk of staff turnover during the course of the project, which may have an impact on the delivery. Which two actions should the project manager take to mitigate this risk? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Meet with management to discuss dividing the project into smaller projects.
  2. B. Convince senior management to hire third-party staff.
  3. C. Enhance the competencies of the project team through training, mentoring, and coaching. — đáp án hiện tại
  4. D. Increase the trained staff to create back-up for resources.
  5. E. Introduce a recognition program to motivate and reward resource performance. — đáp án hiện tại