A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available in 2 weeks due to some unf…

Nội dung câu hỏi

A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available in 2 weeks due to some unforeseen problems. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Apply the terms and conditions of the contract with penalties.
  2. B. Issue a change request to reflect the anticipated date for training.
  3. C. Help the customer find an alternative location to start the training. — đáp án hiện tại
  4. D. Update the project schedule with the new date for training.