Câu 398: Project Management Professional (PMBOK 6 and 7)
An experienced, high-performing team has two new team members. After several iterations with the new team members, the project manager noticed that the team's performance has decreased. What should the project manager do?
Nội dung câu hỏi
An experienced, high-performing team has two new team members. After several iterations with the new team members, the project manager noticed that the team's performance has decreased. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Evaluate the two new team members.
- B. Replace the two new team members.
- C. Provide the team with a coaching session. — đáp án hiện tại
- D. Allow the teams to organize themselves.