Câu 397: Project Management Professional (PMBOK 6 and 7)
A project team is conducting sprint planning. At the end of the sprint, the product increment must be deployed on a customer's site. The product owner received an email from the account manager that the customer may not be ready to install the new version of the product. What should the project manager do?
Nội dung câu hỏi
A project team is conducting sprint planning. At the end of the sprint, the product increment must be deployed on a customer's site. The product owner received an email from the account manager that the customer may not be ready to install the new version of the product. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Ask the sales team to inform the customer.
- B. Contact the customer's project manager. — đáp án hiện tại
- C. Ask the product owner to inform the customer.
- D. Contact the customer's technical lead.