Câu 137: Project Management Professional (PMBOK 6 and 7)

A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented. What should the project manager do?

Nội dung câu hỏi

A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the team member to learn the new system as on-the-job training.
  2. B. Issue a change request to extend the project schedule.
  3. C. Escalate the team member's performance to the project sponsor.
  4. D. Assign an experienced resource to support the team member. — đáp án hiện tại