A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented. What should the project manager do?
Nội dung câu hỏi
A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Ask the team member to learn the new system as on-the-job training.
- B. Issue a change request to extend the project schedule.
- C. Escalate the team member's performance to the project sponsor.
- D. Assign an experienced resource to support the team member. — đáp án hiện tại