Câu 138: Project Management Professional (PMBOK 6 and 7)

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line. How should the project manager address the situation?

Nội dung câu hỏi

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line. How should the project manager address the situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule — đáp án hiện tại
  2. B. Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project
  3. C. Push out the project timeline according to the vacation plan in place based on the recent company policy
  4. D. Discuss the vacation plan and include scheduling changes in the change log database