Câu 325: Project Management Professional (PMBOK 6 and 7)
A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities. What should the project manager do?
Nội dung câu hỏi
A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Review and reassign team assignments
- B. Facilitate communication and team building — đáp án hiện tại
- C. Negotiate for new team members
- D. Review and update the communications management plan