A project team consisting of four team members will be rolling out a company-wide application to both staff and contractors in a country. To deliver within strict the time lines, a local company skilled in application deployment and change management will need to be contracted. What should the project manager do to em…

Nội dung câu hỏi

A project team consisting of four team members will be rolling out a company-wide application to both staff and contractors in a country. To deliver within strict the time lines, a local company skilled in application deployment and change management will need to be contracted. What should the project manager do to empower the local company?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Manage expectations and agree on the requirements that the contractor will deliver under the supervision of the project manager
  2. B. Begin to roll out the application by micromanaging the contractor
  3. C. Set expectations and agree on the requirements that the contractor will deliver with periodic progress reports — đáp án hiện tại
  4. D. Deploy the contractor's staff under the supervision of the project manager