- A. Offer guidance and follow up with some developmental activity for the junior team member. — đáp án hiện tại
- B. Refer the junior team member to the senior team member who develops the risk mitigation strategy.
- C. Inform the junior team member that risk mitigation is not part of their work.
- D. Tell the junior team member that the information is available in lessons learned.