Câu 62: Project Management Professional (PMBOK 6 and 7)

An agile project is in its eighth iteration out of 16. After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply. Which two actions should the project manager take? (Choose two.)

Nội dung câu hỏi

An agile project is in its eighth iteration out of 16. After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply. Which two actions should the project manager take? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the product owner to include the requirements in the product backlog.
  2. B. Ask the security department for details about regulations. — đáp án hiện tại
  3. C. Ask the stakeholders about the priority of this regulation.
  4. D. Ask the team members to include the requirements in the next iteration.
  5. E. Ask the team members to analyze the impact of including this regulation. — đáp án hiện tại