Câu 425: Project Management Professional (PMBOK 6 and 7)
A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed f…
Nội dung câu hỏi
A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for2 days. What does the project manager need to do now?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Inform the product owner
- B. Inform the project sponsor
- C. Inform the relevant stakeholders — đáp án hiện tại
- D. Inform the project team only
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.