Câu 346: Project Management Professional (PMBOK 6 and 7)

Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised. What should the project manager do to ensure success of the project?

Nội dung câu hỏi

Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised. What should the project manager do to ensure success of the project?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Review and prioritize new requirements with stakeholders to determine which change requests are needed. — đáp án hiện tại
  2. B. Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements.
  3. C. Escalate the issue to the project sponsor and seek support to keep the original requirements.
  4. D. Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project.