Câu 345: Project Management Professional (PMBOK 6 and 7)
A project manager is working with the team to deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members, cau…
Nội dung câu hỏi
A project manager is working with the team to deliver a project in a company that uses different delivery methods. The project manager is concerned about the communication channels currently suggested by the project management office (PMO) because some information is taking too much time to reach the team members, causing negative consequences for delivery. How should the project manager avoid this situation in the future?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Agree with the project team on a suitable collaboration and make sure information is shared at all times. — đáp án hiện tại
- B. Use the same methods until the end of the current delivery and suggest new ones during the retrospective.
- C. Refer to the policies and frameworks used at the company enterprise level and inform the project team members.
- D. Tell the sponsor that the project manager will use their own communication model to ensure on-time delivery.