A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no long…
Nội dung câu hỏi
A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Discuss the lack of dedication with the team member and their functional manager
- B. Allow the most senior team members to decide the time that works for the team
- C. Remove the team member from the project team to be fair to the other members
- D. Reassess the team's hours collaboratively so that the team is not impeded by the issue — đáp án hiện tại