Câu 246: Project Management Professional (PMBOK 6 and 7)

An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project. What should t…

Nội dung câu hỏi

An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project. What should the project lead do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask that estimations be provided only by senior developers.
  2. B. Recommend a different estimation method in the retrospective. — đáp án hiện tại
  3. C. Allocate more time for estimation in the sprint planning.
  4. D. Review and update the estimations in the daily standup.