CertyRush
Đang tải...
C CertyRush
Câu hỏi free preview

Câu 247: Project Management Professional (PMBOK 6 and 7)

Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time. What should the project manager do?

Nội dung câu hỏi

Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Reschedule on-site training to online sessions.
  2. B. Document the project issue and provide options. — đáp án hiện tại
  3. C. Create a risk and assign remediation actions.
  4. D. Cancel all of the on-site training sessions.

Cộng đồng

0 bình luận công khai. Tên thành viên được ẩn một phần.

Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.

Câu hỏi liền kề