Câu 308: Project Management Professional (PMBOK 6 and 7)

A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details. What two things should the pr…

Nội dung câu hỏi

A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details. What two things should the project manager do? (Choose two.)

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Discuss the issue with the external supplier's authority.
  2. B. Gather additional information and estimate the impact. — đáp án hiện tại
  3. C. Wait for the client to raise a concern and collect more information.
  4. D. Review the lessons learned from similar past projects.
  5. E. Update the risk log and bring this up in the meeting with the client. — đáp án hiện tại