Câu 309: Project Management Professional (PMBOK 6 and 7)

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog. What should the project manager do?

Nội dung câu hỏi

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the product owner to add the missing feature in the backlog. — đáp án hiện tại
  2. B. Invite stakeholders to discuss the impact of adding the regulatory feature.
  3. C. Estimate the related cost and ask for a project extension.
  4. D. Increase the capacity of the team to include the missed feature.