Câu 310: Project Management Professional (PMBOK 6 and 7)

A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team sh…

Nội dung câu hỏi

A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle. What should the project manager do in this situation?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Assess the team's capacity to absorb the workload
  2. B. Evaluate and understand the cause of the conflict — đáp án hiện tại
  3. C. Escalate the situation to the project sponsor
  4. D. Reject the workload back to the global team