A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have recently been requested. What should the project manager do next?
Nội dung câu hỏi
A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have recently been requested. What should the project manager do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Discuss the changes with the client and jointly make the decision on how to proceed. — đáp án hiện tại
- B. Reject the changes and stay the original course as initially agreed with the client.
- C. Review the risk register to see if mitigations have already been outlined for this scenario.
- D. Review the changes and make the decision based on the project team's recommendations.