Câu 20: Project Management Professional (PMBOK 6 and 7)
During project execution, the project manager discovered that a key deliverable was missing from the scope of work. After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path. What should the project manager do to avoid future delays?
Nội dung câu hỏi
During project execution, the project manager discovered that a key deliverable was missing from the scope of work. After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path. What should the project manager do to avoid future delays?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Submit a change request. — đáp án hiện tại
- B. Add additional resources to the project
- C. Update the scope of work
- D. Review the risk management plan