Câu 19: Project Management Professional (PMBOK 6 and 7)

A new project manager is assigned to a project midway through its implementation. During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using. What should the project manager have done to…

Nội dung câu hỏi

A new project manager is assigned to a project midway through its implementation. During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using. What should the project manager have done to avoid this issue?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Referred to the communications management plan
  2. B. Validated the issue log
  3. C. Validated the project artifacts — đáp án hiện tại
  4. D. Performed expert judgment