Câu 121: Project Management Professional (PMBOK 6 and 7)

During iteration two of a project with two teams (A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized. What should the project…

Nội dung câu hỏi

During iteration two of a project with two teams (A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Cancel the current iteration and reschedule it with the dependent activity.
  2. B. Include the dependent activity in the current iteration for team
  3. C. Ensure team B prioritizes the dependent activity in iteration three. — đáp án hiện tại
  4. D. Assign the two critical activities to team B in iteration two.