Câu 122: Project Management Professional (PMBOK 6 and 7)

In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue. What should the project manager do?

Nội dung câu hỏi

In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ask the human resources (HR) manager to speak with this team member.
  2. B. Coach the team member on how to keep work and personal issues separate.
  3. C. Reallocate this team member's tasks to others for the immediate future.
  4. D. Understand the team member's personal issue and offer them support. — đáp án hiện tại