Câu 72: Project Management Professional (PMBOK 6 and 7)

An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now.…

Nội dung câu hỏi

An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now. What should the project manager do to mitigate this risk?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Extend the sprint end date in anticipation of feedback from the product owner that will require extra work.
  2. B. Schedule an additional interim demo with the product owner. — đáp án hiện tại
  3. C. Address the issue as part of the retrospective.
  4. D. Ask the team to work overtime toward the end of the sprint to meet the original sprint end date.