Câu 73: Project Management Professional (PMBOK 6 and 7)

A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024. What does this value mean for the project?

Nội dung câu hỏi

A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024. What does this value mean for the project?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. The project is earning less value than was planned
  2. B. The project has started exceeding the planned cost — đáp án hiện tại
  3. C. The project has earned more value than planned
  4. D. The project is close to exceeding the planned cost