Câu 195: Project Management Professional (PMBOK 6 and 7)

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case. What should the project manager do?

Nội dung câu hỏi

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case. What should the project manager do?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Ensure the client representative is involved in the estimation.
  2. B. Ensure that a 20% contingency is included in the estimation.
  3. C. Review the completion costs of similar projects. — đáp án hiện tại
  4. D. Review the lessons learned from similar projects.