Câu 194: Project Management Professional (PMBOK 6 and 7)
A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks. What should the project manager do?
Nội dung câu hỏi
A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks. What should the project manager do?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Create a new standard performance measure based on project requirements
- B. Develop different approaches based on team members' motivation and ability — đáp án hiện tại
- C. Develop a standard approach to provide feedback to all team members
- D. Provide intensive oversight to the team members who performed poorly