Câu 193: Project Management Professional (PMBOK 6 and 7)

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration…

Nội dung câu hỏi

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After 3 days of work, the project manager completed two actions and spent US$80,000. What should the project manager do next?

Các lựa chọn

Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.

  1. A. Complete all actions and then inform the client of the additional cost and schedule overrun needed to complete the project
  2. B. Stop the work and raise a project change request to the change control board (CCB) for additional funds and a project schedule extension
  3. C. As the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions
  4. D. As the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0, reevaluate and prioritize the remaining actions — đáp án hiện tại