Câu 132: Project Management Professional (PMBOK 6 and 7)
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team. What should the project manager do next?
Nội dung câu hỏi
During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team. What should the project manager do next?
Các lựa chọn
Đáp án được giữ gọn theo nhãn A, B, C, D trong phần bình chọn tương tác.
- A. Request the scrum team to prioritize the product backlog
- B. Ask the product owner to prioritize the backlog with the project team — đáp án hiện tại
- C. Call for an internal meeting to discuss the changes and their value
- D. Incorporate the changes in the last sprint before the first release
Cộng đồng
0 bình luận công khai. Tên thành viên được ẩn một phần.
Chưa có bình luận. Mở giao diện tương tác để bắt đầu thảo luận.